Company Benefits Solutions Testimonials Contact Us
Client satisfaction

What contractors, developers and consultants say about working with Waja Law

Feedback from clients who have engaged Waja Law for contract review, CIPAA adjudication and construction disputes in Malaysia.

Back to Home

Testimonials from construction industry clients

"We brought in Waja Law to review a CIDB sub-contract before we signed. The commentary they produced was useful — it identified an LAD clause that had no genuine cap on exposure, which we hadn't caught ourselves. The output was clear enough for our commercial director to use directly in the negotiation."

AM

Ahmad Muzakkir

Contracts Manager — Subang Jaya

March 2025

"We received a CIPAA payment claim and had about ten working days to respond. Waja Law picked up the file quickly, identified two jurisdictional issues worth raising, and produced the Payment Response and Adjudication Response within the statutory windows. The process was tighter than I expected — more structured than dealing with a general litigation firm."

LP

Lim Pei Yee

Project Director — Petaling Jaya

February 2025

"I appreciated that they told us at the start which parts of our delay claim were well-supported and which weren't. We ended up refining the claim considerably before filing. It was better advice than being told everything looked fine — we went in with realistic expectations and a cleaner submission."

RN

Rajan Nair

Senior QS — Shah Alam

January 2025

"The fee was fixed and clearly stated before they started the contract review. That was the main reason we chose them — we had a budget for the review and needed to know the cost wouldn't change. The commentary covered exactly what we needed for the negotiation."

FZ

Farah Zulaikha

Development Manager — Cyberjaya

March 2025

"We had a CIPAA adjudication decision in our favour and needed advice on enforcing it. Waja Law explained the enforcement process clearly and handled the High Court application. The process was more straightforward than I expected, partly because the decision itself was well-structured — their submission at adjudication stage had made enforcement easier."

TH

Tan Hock Weng

Director — M&E Contractor, Klang

April 2025

"We had a final account dispute that had been stuck for two years. After reviewing the documents, they were straightforward about which items had strong contractual support and which were weaker. We ended up negotiating a settlement after the Adjudication Response was filed — the other side had clearly reassessed their position after reading our submissions."

SI

Siti Norzahra Ibrahim

Operations Head — Civil Contractor, Putrajaya

February 2025

Three construction matters handled in detail

CIPAA claim for interim payment — retained sum not released

CHALLENGE

A specialist subcontractor had completed their scope on a commercial building in Shah Alam. The main contractor withheld RM 280,000 in certified amounts citing set-off for alleged defects, without serving a proper Payment Response within the statutory period.

APPROACH

Waja Law filed a CIPAA Payment Claim and, when the respondent served a late Payment Response, raised the jurisdictional issue in the Adjudication Claim. Full written submissions on the merits of the set-off were prepared in the alternative.

OUTCOME

The adjudicator upheld the claim on jurisdictional and merits grounds. The full sum was awarded. Enforcement through the High Court was straightforward as the respondent did not contest the decision.

TIMELINE

Referral to decision: 11 weeks

PAM contract review before execution — data centre fit-out

CHALLENGE

A main contractor was asked to sign a heavily amended PAM Contract 2018 for a RM 12 million data centre fit-out. The employer had introduced amendments removing the standard EOT provisions and capping the contractor's right to payment for variations below a threshold.

APPROACH

Waja Law produced a marked-up commentary covering the amendments most likely to affect the contractor's financial exposure — particularly the LAD provisions, the variation threshold, and the modified dispute escalation clause which attempted to exclude CIPAA.

OUTCOME

The contractor negotiated amendments to the LAD cap, reinstatement of standard EOT notice requirements, and removal of the clause purporting to restrict CIPAA rights (which in any event could not legally override the statute).

TIMELINE

Review delivered: 7 working days

Arbitration — delay and prolongation claim, infrastructure project

CHALLENGE

A contractor was defending a RM 2.4 million LAD claim by an employer following a 14-month delay on a drainage infrastructure project. The contractor's position was that the delay was caused by late design information and an instruction to vary the specification during construction.

APPROACH

Waja Law engaged a forensic delay analyst to prepare a time impact analysis demonstrating critical path impact. The legal submissions built on the delay analysis and the documentary record of requests for information, showing that the contractor had complied with notice requirements.

OUTCOME

The arbitrator awarded an extension of time of 9 months, reducing the LAD exposure from RM 2.4 million to RM 375,000. The prolongation counterclaim for site overhead costs was partially allowed.

TIMELINE

Hearing to award: 14 months

By the numbers

85+

Contracts reviewed

40+

CIPAA proceedings

4.7

Average client rating

MY Bar

Practising certificate

Reach us directly

Address

Suite 2-2, Tamarind Square, Persiaran Multimedia, 63000 Cyberjaya

Hours

Mon–Fri 9:00–18:00
Sat 9:00–13:00

Tell us about your construction matter

Contract review, CIPAA proceedings, or a larger dispute — we review documents before advising, so please send us what you have.

Get in Touch